On September 18, a concrete pump truck backed up to the fenced construction zone at the foot of 12th Avenue South and finished pouring the mid-Pavilion, the midpoint shelter that once held Cosmos on the Pier. That single pour pushed the Naples Pier rebuild past the 50 percent mark for total concrete placement on the entire structure, according to the City of Naples' own project log. Most residents who pass that stretch of Gulf Shore Boulevard have mentally filed the pier under "still closed, ask again later." The construction log tells a different story: this is a project running on a real, dated schedule, and the shape of what's visible from the sand is about to change fast heading into snowbird season.
That distinction matters because the pier has been closed long enough, since Hurricane Ian tore through in September 2022, that "closed" started to feel like a permanent condition rather than a phase with an end. It isn't. Shoreline Foundation Inc., the Broward County marine contractor building the new structure, has been logging dated milestones every few weeks since spring, and reading them in order shows a project accelerating, not stalling.
The Six Months That Got Naples Here
The pace this year has been faster than the pier's multi-year planning phase might suggest. Here's what the city's own timeline shows for 2026:
| Date | Milestone |
|---|---|
| January 2026 | Groundbreaking ceremony marks the official start of construction |
| April 24, 2026 | Crews deploy 59 concrete pilings at Wasmer Reef, expanding an artificial reef first established in 2015 |
| May 5, 2026 | Shoreline Foundation begins a month-long diving initiative to clear buried 1990s-era pilings ahead of new pile installation |
| June 17, 2026 | Crews begin assembling the trestle, a bridge-like walkway on the pier's south side that lets work continue even when offshore barges have to shelter from weather |
| June 26, 2026 | First concrete pour for the bents, the angled pilings capped by a crossbeam that support the deck |
| September 18, 2026 | Concrete pour for the mid-Pavilion completed, pushing total concrete placement past 50 percent |
A few things stand out in that sequence. The Wasmer Reef detail means the old pier isn't just being hauled to a landfill. City officials have said that roughly 30 to 40 percent of the demolished concrete is being recycled into highway material, and some of it is going straight into expanding an artificial reef that anglers and divers have used since 2015. For a town where fishing off the pier was a daily ritual for a lot of residents, that's a more useful ending for the old material than most people probably assumed.
The trestle, installed in June, is also the reason work hasn't stopped every time a summer storm rolls through. It gives Shoreline Foundation a stable platform to keep pouring concrete and setting pilings even when the barges that would normally handle that work have to pull back from open water. That's part of why the pace held through hurricane season instead of losing months to weather delays.
Why the November Date You Might Have Heard Is the Wrong One
If you've heard a completion date floating around and it was November 2026, that number is real but it isn't pointing at the part of the project most people care about. In December 2024, the Naples City Council approved a contract amendment with Turrell, Hall & Associates, the ocean engineering firm overseeing design, that extended their engineering services contract to November 15, 2026, largely to accommodate federal permitting timelines. That date describes when the engineering firm's oversight contract runs through. It was never a construction completion date.
Actual construction didn't break ground until the January 2026 groundbreaking ceremony, and the project has been described consistently as an 18-month build from that start. Run the math forward from January 2026 and the more realistic completion window lands in the middle of 2027, not this coming November. Large public works projects can still slip in either direction, and the city has said as much itself, but the mechanism behind the date confusion is straightforward: one date belongs to a paperwork contract, the other belongs to the concrete and pilings actually going into the Gulf.
What Beach Access Looks Like Right Now
None of this affects your ability to get to the sand. The pier structure itself, the stairs, restrooms, and showers, and the stretch of 12th Avenue South west of Gulf Shore Boulevard South are closed for the duration of construction. But the city set up two pedestrian bypasses specifically to keep beach access open through the whole project, at the Broad Avenue South and 13th Avenue South beach ends, both with their own restrooms. The western third of the pier parking lot is still open to the public too, while the eastern two-thirds stays fenced for staging equipment.
So the walk to the water hasn't really changed. What's changed is what you'll see when you get there: a construction zone that's visibly more than half-poured, with the mid-Pavilion's frame now standing where the old concession stand used to sit.
Where Locals Are Rerouting a Sunset Walk
For anyone who used to end an evening at the pier's railing, a few nearby spots cover the same ground without the fencing:
- Baker Park, at the north end of the Gordon River Greenway, sits at a high point with views back toward Old Naples and makes a natural turnaround point for an evening walk.
- The Gordon River Greenway itself runs about 2.5 miles on paved and boardwalk trail through mangrove and pine flatwoods, and it has its own fishing piers along the Gordon River for anyone who lost their usual casting spot when the ocean pier closed.
- The beach beneath the old pier, reached through either bypass, is unchanged for sunset watching. Only the structure above the sand is off limits.
None of these replace the pier's specific view straight out into the Gulf, but they cover the same daily habits, the evening walk, the dog on a leash, the spot to watch the sky change color, without waiting on a fence to come down.
What to Actually Watch For This Fall
The pace of the last six months suggests the visible progress from the beach is going to keep accelerating rather than plateau. If the mid-Pavilion's concrete work is done and the project has crossed 50 percent, the next stretch of construction is likely to bring the pier's outline back into view for the first time since Ian, even with the decking and the end shelter still to come. The city posts dated updates directly on its project page, and given how often new milestones have landed this year, it's worth checking back before assuming nothing has moved since the last time you looked.
If you've been meaning to walk past the pier site and see how the mid-Pavilion actually looks now that it's poured, or you just want someone who tracks these updates as closely as the people building it, Gina Guarino Group walks this stretch of coast as much as anyone in town. Let Our Team, Be Your Team.